Cameron LNG
301 N. Main St.
Hackberry LA 70645
3375275240
| Randy Oakley |
Kim Byrley |
| Terminal Manager |
Administrative Assistant |
| 3376804519 |
3376804523 |
|
|
General Plant Information
- On the Calcasieu Channel, 18 miles from the Gulf of Mexico in Hackberry, La.
- Owned 100 percent by Sempra Energy; represents a capital investment of about US $900M
- 1.5 billion cubic feet per day of initial send out capacity, with room for expansion.
- 35 miles from a major pipeline hub that provides access to nearly two-thirds of all U.S. natural gas markets.
- Three full-containment storage tanks (3 x 160,000 cubic meters); two ship berths.
- Fully permitted; capacity 40 percent contracted.
- Construction began in August 2005.
- Commercial operations began in July 2009.